پروژه ها

شماره توضیحات کارفرما نوع پروژه نوع دکل سال ساخت
1 Line 132 KV (shosh-hafttapeh ) Khuzestan regional electric Production LS2-3,T2-30,T2-60 2022
2 Line 132 KV (Bagh Malek ) Khuzestan regional electric Production LS2-3,T2-30,HS2-10 2022
3 63 KV , 4 circuit power Esfahan regional electric Production NN-AA-CC 2021
4 Line 132 KV (Shayban- Hashemi ) Khuzestan regional electric Production LS2-3,S1KL, T1-60 2020
5 Line 230 KV (2 circuit) Khuzestan regional electric Production LS2-3,T2-30,T2-60 2018
6 Line 230 KV (2 circuit Dezfol- sardasht) Khuzestan regional electric Production LS2-3,T2-30,T2-61 2018
7 Design , Construction , testing the 4 circuit 230 power towers Bakhtar regional electric Design/production/installat ion DC30/60-DC90-DT60- TQC30-DTQC60-SQ03- TQC10 2016
8 63 KV , 4 circuit power towers for (shahabiyehkhomeyn line) Bakhtar regional electri production NN-AA-CC 2016
9 132 KV, 2 circiut power towers for (KedarMohammad abad line) Khuzestan regional electric Production / Sorting HS2-10 2015
10 230KV power towers for Mahshahr Khuzestan regional electric Production / Sorting LS2-3-T230-T2-60 2015
11 63 KV , 2 Circuit Power towers for (Firouz Abad line) Eghlim Yab Zagros Co. Production NN-AA-CC 2014
12 230 KV , 2 Circuit Power towers for (Chorazagh line) Satel Raham Co. Production DC0-DC10-DC30/60-DC90 2013
13 Construction, installation and stringing of 63 KV 4 circuit power towers of (Aveh line) Bakhtar regional electric Production / installation/stringing/full Maintenance QS03-QT30-QT60 2013
14 Construction of 132 KV power towers Khuzestan Power Transmission Maintenance and Repairs Production / Sorting MS-HS 2012
15 63 KV power towers for (Zaviyeh Industrial Zone line) Bakhtar regional electric Production / installation/stringing/full Maintenance NN-AA-CC-DC0-DC10- DC60 2012
16 63 KV power towers for (Saveh line No 88/57 ) Bakhtar regional electric Production / installation/stringing/full Maintenance QS03-QT30-QT60 2011
17 Construction, installation and stringing of 63 KV power towers for (kaghaz sazi line no 88/2) Bakhtar regional electric Production / installation/stringing/full Maintenance NN-AA-CC 2011
18 Construction, installation and stringing of 63 , 230 KV 4 circuit power towers for(Malayer -jokar line) Bakhtar regional electric Production / installation/stringing/full Maintenance QS03-QT30-QT60 2011
19 Construction, installation and stringing of 63 power towers for (Javersiyan line) Bakhtar regional electric Production / installation/stringing/full Maintenance NN-AA-CC 2011
20 63 KV Power towers for (Saveh -Mamoniyeh line ) Bakhtar regional electric Production / installation/stringing/full Maintenance NN-AA-CC 2011
21 Construction, installation and stringing of 63 power towers for(Khomein - Mahalat line) Bakhtar regional electric Production / installation/stringing/full Maintenance NN-AA-CC 2010
22 63 KV Power towers for (oil production regions line ) Jarf Kar Jam Co. Production NN-AA-CC 2009
23 230 KV power towers for (Ray - Tabriz line ) Parsian Co. Production DC0-DC10-DC30/60-DC90 2009
24 63 KV Power towers for (Ardestan Steel Project line ) Safa nikoo Co. Production NN-AA-CC 2008
25 400 KV Power Towers for ( Ali Abad line) Emkan Electric Co. Production T1K15-T1K45-T1K90 2008
26 63 KV Power towers for (Fajr Sepahan Galvanization project line ) Safa nikoo Co. Safa nikoo Co. NN-AA-CC 2007
27 63 KV Power towers for (Kashan Cement project line ) Matba Co. Production / Sorting NN-AA-CC 2007
28 400 KV Power Towers for (Omidiyeh - Karoon line) Emkan Electric Co. Production T2K,T2K15,T2K45,S2KL 2006